This work had as initial implementation deadline of 14 September and it was completed on 30 June. "Record period" said David Santos, project director of the work.
"The work began July 7, having been established in a month, we had to coordinate lots by providing two per week (including paintings, milling and paving), something difficult with the movement that lives daily at the airport, never able to even stop or even slow down, we had to operate at night, "concluded David Santos.